12 May, 2020
Published 12 May 2020 08:52
There are no violations of NPP safe operation limits and
conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal
mode.
NPP security divisions and physical protection services
are on high alert.
Unit Number | Unit status | Аverage dose rate on an industrial site(µSv/h) |
Zaporizhzhya NPP | ||
1 | Power 975 MW (el.) | |
2 | Power 680 MW (el.) | |
3 | In outage till 24.05.2020 | 0,11 |
4 | In outage till 01.09.2020 | |
5 | In outage till 14.11.2020 | |
6 | Power 845 MW (el.) | |
Rivno NPP | ||
1 | Power 420 MW (el.) | |
2 | Power 405 MW (el.) | 0,10 |
3 | Power 940 MW (el.) | |
4 | In reserve until 12.05.2020 | |
| ||
1 | Power 1010 MW (el.) | |
2 | Power 590 MW (el.) | 0,12 |
South Ukrainian NPP | ||
1 | Power 800 MW (el.) | |
2 | In outage till 31.07.2020 | 0,12 |
3 | Power 600 MW (el.) | |
Chornobyl NPP | ||
Decommissioning | 0,25 |
Performance indicator of NPP Units: