07 August,2020
Published 07 August 2020 09:40
There are no violations of NPP safe operation limits and
conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal
mode.
NPP security divisions and physical protection services
are on high alert.
Unit Number | Unit status | Аverage dose rate on an industrial site(µSv/h) |
Zaporizhzhya NPP | ||
1 | In reserve until 07.08.2020 | |
2 | Power 675 MW (el.) | |
3 | Power 980 MW (el.) | 0,11 |
4 | In outage till 01.09.2020 | |
5 | In outage till 14.11.2020 | |
6 | Power 985 MW (el.) | |
Rivno NPP | ||
1 | Power 420 MW (el.) | |
2 | Power 395 MW (el.) | 0,10 |
3 | Power 975 MW (el.) | |
4 | Power 995 MW (el.) | |
| ||
1 | In outage till 09.08.2020 | |
2 | Power 830 MW (el.) | 0,12 |
South Ukrainian NPP | ||
1 | In outage till 29.09.2020 | |
2 | Power 950 MW (el.) | 0,11 |
3 | Power 650 MW (el.) | |
Chornobyl NPP | ||
Decommissioning | 0,37 |
Performance indicator of NPP Units: