05 August,2020
Published 05 August 2020 10:52
There are no violations of NPP safe operation limits and
conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal
mode.
NPP security divisions and physical protection services
are on high alert.
Unit Number | Unit status | Аverage dose rate on an industrial site(µSv/h) |
Zaporizhzhya NPP | ||
1 | In reserve until 07.08.2020 | |
2 | Power 675 MW (el.) | |
3 | Power 980 MW (el.) | 0,08 |
4 | In outage till 01.09.2020 | |
5 | In outage till 14.11.2020 | |
6 | Power 985 MW (el.) | |
Rivno NPP | ||
1 | Power 420 MW (el.) | |
2 | Power 400 MW (el.) | 0,10 |
3 | Power 720 MW (el.) | |
4 | Power 1000 MW (el.) | |
| ||
1 | In outage till 09.08.2020 | |
2 | Power 870 MW (el.) | 0,12 |
South Ukrainian NPP | ||
1 | In outage till 29.09.2020 | |
2 | Power 950 MW (el.) | 0,12 |
3 | Power 600 MW (el.) | |
Chornobyl NPP | ||
Decommissioning | 0,35 |
Performance indicator of NPP Units: