There are no violations of NPP safe operation limits and conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal mode.
NPP security divisions and physical protection services are on high alert.
Unit Number |
Unit status |
Аverage dose rate on an industrial site(µSv/h) |
Zaporizhzhya NPP |
||
1 |
Power 970 MW (el.) |
|
2 |
In outage till 11.11.2020 |
|
3 |
Power 1005 MW (el.) |
0,11 |
4 |
In outage till 15.10.2020 |
|
5 |
In outage till 14.11.2020 |
|
6 |
Power 1010 MW (el.) |
|
Rivno NPP |
||
1 |
Power 430 MW (el.) |
|
2 |
Power 420 MW (el.) |
0,10 |
3 |
Power 910 MW (el.) |
|
4 |
In outage till 09.01.2021 |
|
Khmelnitsky NPP |
||
1 |
Power 1010 MW (el.) |
|
2 |
In outage till 14.03.2021 |
0,12 |
South Ukrainian NPP |
||
1 |
Power 880 MW (el.) |
|
2 |
Power 1000 MW (el.) |
0,11 |
3 |
Power 840 MW (el.) |
|
Chornobyl NPP |
||
Decommissioning |
0,30 |
Performance indicator of NPP Units: