31 May, 2020
Published 31 May 2020 20:46
There are no violations of NPP safe operation limits and
conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal
mode.
NPP security divisions and physical protection services
are on high alert.
Unit Number | Unit status | Аverage dose rate on an industrial site(µSv/h) |
Zaporizhzhya NPP | ||
1 | Power 600 MW (el.) | |
2 | Power 920 MW (el.) | |
3 | In outage till 31.05.2020 | 0,11 |
4 | In outage till 01.09.2020 | |
5 | In outage till 14.11.2020 | |
6 | Power 600 MW (el.) | |
Rivno NPP | ||
1 | Power 425 MW (el.) | |
2 | Power 405 MW (el.) | 0,10 |
3 | In reserve until 04.08.2020 | |
4 | Power 1000 MW (el.) | |
Khmelnitsky NPP | ||
1 | Power 870 MW (el.) | |
2 | Power 580 MW (el.) | 0,12 |
South Ukrainian NPP | ||
1 | Power 600 MW (el.) | |
2 | In outage till 31.07.2020 | 0,12 |
3 | Power 600 MW (el.) | |
Chornobyl NPP | ||
Decommissioning | 0,3 |
Performance indicator of NPP Units: