31 August, 2019
Published 31 August 2019 16:44
There are no violations of NPP safe operation limits and conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal mode.
NPP security divisions and physical protection services are on high alert.
Unit Number | Unit status | On-site radiation level (µR/hour) |
Zaporizhzhya NPP | ||
1 | Power 880 MW (el.) | |
2 | Power 970 MW (el.) | |
3 | Power 990 MW (el.) | 11 |
4 | Power 980 MW (el.) | |
5 | In outage till 27.09.19 | |
6 | Power 980 MW (el.) | |
Rivno NPP | ||
1 | Power 390 MW (el.) | |
2 | Power 390 MW (el.) | 10 |
3 | In outage till 14.09.19 | |
4 | In outage till 19.10.19 | |
| ||
1 | In outage till 20.11.19 | |
2 | Power 750 MW (el.) | 12 |
South Ukrainian NPP | ||
1 | In outage till 19.10.19 | |
2 | Power 975 MW (el.) | 11,2 |
3 | In outage till 17.11.19 | |
Chornobyl NPP | ||
Decommissioning |
Performance indicator of NPP Units: