28 August, 2019
Published 28 August 2019 16:28
There are no violations of NPP safe operation limits and conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal mode.
NPP security divisions and physical protection services are on high alert.
Unit Number | Unit status | On-site radiation level (µR/hour) |
Zaporizhzhya NPP | ||
1 | Power 890 MW (el.) | |
2 | Power 960 MW (el.) | |
3 | Power 970 MW (el.) | 12 |
4 | Power 970 MW (el.) | |
5 | In outage till 27.09.19 | |
6 | Power 980 MW (el.) | |
Rivno NPP | ||
1 | Power 395 MW (el.) | |
2 | Power 395 MW (el.) | 10 |
3 | In outage till 14.09.19 | |
4 | In outage till 19.10.19 | |
| ||
1 | In outage till 20.11.19 | |
2 | Power 600 MW (el.) | 12 |
South Ukrainian NPP | ||
1 | Power 675 MW (el.) | |
2 | Power 995 MW (el.) | 12 |
3 | In outage till 17.11.19 | |
Chornobyl NPP | ||
Decommissioning |
Performance indicator of NPP Units: