27 August, 2017
Published 27 August 2017 06:01
There are no violations of NPP safe operation limits and conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal mode.
NPP security divisions and physical protection services are on high alert.
Unit Number | Unit status | On-site radiation level (µR/hour) |
Zaporizhzhya NPP | ||
1 | In outage till 30.11.17 | 11,0 |
2 | Power 600 MW (el.) | |
3 | In outage till 13.11.17 | |
4 | In outage till 24.09.17 | |
5 | Power 955 MW (el.) | |
6 | Power 995 MW (el.) | |
Rivno NPP | ||
1 | Power 415 MW (el.) | 10,0 |
2 | Power 415 MW (el.) | |
3 | Power 950 MW (el.) | |
4 | Power 300 MW (el.) | |
South Ukrainian NPP | ||
1 | In outage till 04.10.17 | 11,8 |
2 | Power 1000 MW (el.) | |
3 | Power 965 MW (el.) | |
| ||
1 | Power 650 MW (el.) | 12,0 |
2 | Power 670 MW (el.) | |
Chornobyl NPP | ||
Decommissioning | 30,0 |