26 March, 2017
Published 26 March 2017 07:35
There are no violations of NPP safe operation limits and conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal mode.
NPP security divisions and physical protection services are on high alert.
Unit Number | Unit status | On-site radiation level (µR/hour) |
Zaporizhzhya NPP | ||
1 | Power 980 MW (el.) | 12,0 |
2 | Power 980 MW (el.) | |
3 | In outage till 12.11.17 | |
4 | Power 990 MW (el.) | |
5 | Power 1000 MW (el.) | |
6 | Power 920 MW (el.) | |
Rivno NPP | ||
1 | Power 220 MW (el.) | 9,0 |
2 | Power 430 MW (el.) | |
3 | In outage till 01.04.17 | |
4 | Power 995 MW (el.) | |
South Ukrainian NPP | ||
1 | Power 950 MW (el.) | 11,7 |
2 | Power 615 MW (el.) | |
3 | Power 750 MW (el.) | |
| ||
1 | Power 1010 MW (el.) | 12,0 |
2 | Power 1010 MW (el.) | |
Chornobyl NPP | ||
Decommissioning | 30,0 |