26 July, 2020
Published 26 July 2020 16:30
There are no violations of NPP safe operation limits and
conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal
mode.
NPP security divisions and physical protection services
are on high alert.
Unit Number | Unit status | Аverage dose rate on an industrial site(µSv/h) |
Zaporizhzhya NPP | ||
1 | In reserve until 31.07.2020 | |
2 | Power 670 MW (el.) | |
3 | Power 930 MW (el.) | |
4 | In outage till 01.09.2020 | |
5 | In outage till 14.11.2020 | |
6 | Power 990 MW (el.) | |
Rivno NPP | ||
1 | Power 425 MW (el.) | |
2 | Power 400 MW (el.) | 0,10 |
3 | In reserve until 04.08.2020 | |
4 | Power 1000 MW (el.) | |
| ||
1 | Power 1014 MW (el.) | |
2 | Power 956 MW (el.) | 0,12 |
South Ukrainian NPP | ||
1 | Power 900 MW (el.) | |
2 | Power 650 MW (el.) | 0,12 |
3 | In outage till 03.08.2020 | |
Chornobyl NPP | ||
Decommissioning | 0,30 |
Performance indicator of NPP Units: