24 May, 2020
Published 24 May 2020 10:07
There are no violations of NPP safe operation limits and
conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal
mode.
NPP security divisions and physical protection services
are on high alert.
Unit Number | Unit status | Аverage dose rate on an industrial site(µSv/h) |
Zaporizhzhya NPP | ||
1 | Power 600 MW (el.) | |
2 | Power 1020 MW (el.) | |
3 | In outage till 31.05.2020 | 0,12 |
4 | In outage till 01.09.2020 | |
5 | In outage till 14.11.2020 | |
6 | Power 780 MW (el.) | |
Rivno NPP | ||
1 | Power 445 MW (el.) | |
2 | Power 420 MW (el.) | 0,10 |
3 | In reserve until 04.08.2020 | |
4 | Power 1005 MW (el.) | |
Khmelnitsky NPP | ||
1 | Power 1010 MW (el.) | |
2 | Power 590 MW (el.) | 0,12 |
South Ukrainian NPP | ||
1 | Power 750 MW (el.) | |
2 | In outage till 31.07.2020 | 0,12 |
3 | Power 600 MW (el.) | |
Chornobyl NPP | ||
Decommissioning | 0,34 |
Performance indicator of NPP Units: