24 August, 2019
Published 27 August 2019 10:26
There are no violations of NPP safe operation limits and conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal mode.
NPP security divisions and physical protection services are on high alert.
Unit Number | Unit status | On-site radiation level (µR/hour) |
Zaporizhzhya NPP | ||
1 | Power 910 MW (el.) | 11 |
2 | Power 960 MW (el.) | |
3 | Power 970 MW (el.) | |
4 | Power 970 MW (el.) | |
5 | In outage till 27.09.19 | |
6 | Power 970 MW (el.) | |
Rivno NPP | ||
1 | Power 400 MW (el.) | 10 |
2 | Power 400 MW (el.) | |
3 | In outage till 14.09.19 | |
4 | In outage till 19.10.19 | |
| ||
1 | In outage till 23.08.19 | 12 |
2 | Power 600 MW (el.) | |
South Ukrainian NPP | ||
1 | Power 680 MW (el.) | 12 |
2 | Power 995 MW (el.) | |
3 | In outage till 17.11.19 | |
Chornobyl NPP | ||
Decommissioning |
Performance indicator of NPP Units: