21 June, 2018
Published 21 June 2018 07:50
There are no violations of NPP safe operation limits and conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal mode.
NPP security divisions and physical protection services are on high alert.
Unit Number | Unit status | On-site radiation level (µR/hour) |
Zaporizhzhya NPP | ||
1 | Power 900 MW (el.) | |
2 | Power 940 MW (el.) | 11 |
3 | Power 980 MW (el.) | |
4 | In outage till 26.10.18 | |
5 | In outage till 04.08.18 | |
6 | Power 1000 MW (el.) | |
Rivno NPP | ||
1 | Power 405 MW (el.) | |
2 | Power 410 MW (el.) | |
3 | In outage till 04.08.18 | |
4 | Power 985 MW (el.) | |
| ||
1 | Power 990 MW (el.) | |
2 | Power 980 MW (el.) | 12 |
South Ukrainian NPP | ||
1 | Power 920 MW (el.) | |
2 | Power 970 MW (el.) | 11.7 |
3 | In outage till 19.07.18 | |
Chornobyl NPP | ||
Decommissioning | 36 |