19 August, 2018
Published 20 August 2018 09:17
There are no violations of NPP safe operation limits and conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal mode.
NPP security divisions and physical protection services are on high alert.
Unit Number | Unit status | On-site radiation level (µR/hour) |
Zaporizhzhya NPP | ||
1 | Power 885 MW (el.) | |
2 | Power 930 MW (el.) | 12 |
3 | Power 970 MW (el.) | |
4 | In outage till 26.10.18 | |
5 | Power 950 MW (el.) | |
6 | Power 985 MW (el.) | |
Rivno NPP | ||
1 | Power 410 MW (el.) | |
2 | Power 410 MW (el.) | 10 |
3 | Power 930 MW (el.) | |
4 | In outage till 05.09.18 | |
| ||
1 | Power 980 MW (el.) | |
2 | Power 970 MW (el.) | 12 |
South Ukrainian NPP | ||
1 | In outage till 17.10.18 | |
2 | Power 825 MW (el.) | 11,7 |
3 | Power 950 MW (el.) | |
Chornobyl NPP | ||
Decommissioning |