18 August, 2017
Published 18 August 2017 07:24
There are no violations of NPP safe operation limits and conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal mode.
NPP security divisions and physical protection services are on high alert.
Unit Number | Unit status | On-site radiation level (µR/hour) |
Zaporizhzhya NPP | ||
1 | Power 680 MW (el.) | 11,0 |
2 | Power 600 MW (el.) | |
3 | In outage till 13.11.17 | |
4 | In outage till 24.09.17 | |
5 | Power 950 MW (el.) | |
6 | Power 980 MW (el.) | |
Rivno NPP | ||
1 | Power 400 MW (el.) | 10,0 |
2 | Power 400 MW (el.) | |
3 | Power 940 MW (el.) | |
4 | In outage till 25.08.17 | |
South Ukrainian NPP | ||
1 | In outage till 04.10.17 | 12,0 |
2 | Power 990 MW (el.) | |
3 | Power 960 MW (el.) | |
| ||
1 | Power 650 MW (el.) | 12,0 |
2 | Power 730 MW (el.) | |
Chornobyl NPP | ||
Decommissioning | 60,0 |