11 May, 2019
Published 11 May 2019 10:56
There are no violations of NPP safe operation limits and conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal mode.
NPP security divisions and physical protection services are on high alert.
Unit Number | Unit status | On-site radiation level (µR/hour) |
Zaporizhzhya NPP | ||
1 | Power 960 MW (el.) | |
2 | In outage till 18.08.19 | |
3 | Power 1000 MW (el.) | 11 |
4 | In outage till 14.06.19 | |
5 | Power 980 MW (el.) | |
6 | Power 1010 MW (el.) | |
Rivno NPP | ||
1 | Power 415 MW (el.) | |
2 | Power 415 MW (el.) | 10 |
3 | Power 960 MW (el.) | |
4 | Power 1010 MW (el.) | |
| ||
1 | In outage till 06.08.19 | |
2 | Power 1010 MW (el.) | 12 |
South Ukrainian NPP | ||
1 | Power 1000 MW (el.) | |
2 | In outage till 03.07.19 | 11,8 |
3 | Power 980 MW (el.) | |
Chornobyl NPP | ||
Decommissioning | 28 |
Performance indicator of NPP Units: