10 July, 2019
Published 10 July 2019 13:30
There are no violations of NPP safe operation limits and conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal mode.
NPP security divisions and physical protection services are on high alert.
Unit Number | Unit status | On-site radiation level (µR/hour) |
Zaporizhzhya NPP | ||
1 | Power 915 MW (el.) | |
2 | In outage till 18.08.19 | |
3 | Power 985 MW (el.) | 11 |
4 | Power 975 MW (el.) | |
5 | In outage till 27.09.19 | |
6 | Power 990 MW (el.) | |
Rivno NPP | ||
1 | Power 410 MW (el.) | |
2 | Power 400 MW (el.) | 11 |
3 | In outage till 14.09.19 | |
4 | Power 980 MW (el.) | |
| ||
1 | In outage till 06.08.19 | |
2 | Power 995 MW (el.) | 12 |
South Ukrainian NPP | ||
1 | Power 700 MW (el.) | |
2 | Power 990 MW (el.) | 12 |
3 | In outage till 17.11.19 | |
Chornobyl NPP | ||
Decommissioning | 35 |
Performance indicator of NPP Units: