10 July, 2018
Published 10 July 2018 10:50
There are no violations of NPP safe operation limits and conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal mode.
NPP security divisions and physical protection services are on high alert.
Unit Number | Unit status | On-site radiation level (µR/hour) |
Zaporizhzhya NPP | ||
1 | Power 900 MW (el.) | |
2 | Power 935 MW (el.) | 11 |
3 | Power 975 MW (el.) | |
4 | In outage till 26.10.18 | |
5 | In outage till 04.08.18 | |
6 | Power 990 MW (el.) | |
Rivno NPP | ||
1 | Power 370 MW (el.) | |
2 | Power 400 MW (el.) | 10 |
3 | In outage till 04.08.18 | |
4 | In outage till 05.09.18 | |
| ||
1 | Power 1000 MW (el.) | |
2 | Power 980 MW (el.) | 12 |
South Ukrainian NPP | ||
1 | Power 820 MW (el.) | |
2 | Power 980 MW (el.) | 11,5 |
3 | In outage till 19.07.18 | |
Chornobyl NPP | ||
Decommissioning | 30 |