09 May, 2016
Published 10 May 2016 09:48

There are no violations of NPP safe operation limits and conditions.

Radioactive situation meets established norms.

Systems of NPP physical protection work in normal mode.

NPP security divisions and physical protection services are on high alert.

 

 

Unit

Number

 

Unit status

 

On-site radiation levelR/hour)

Zaporizhzhya NPP

1

In outage till 25.05.16

11,0

2

In outage till 29.05.16

3

In outage till 05.07.16

4

Power 0 MW (el.)

5

Power 620 MW (el.)

6

Power 1020 MW (el.)

Rivno NPP

1

Power 410 MW (el.)

10,0

2

In outage till 04.06.16

3

Power 990 MW (el.)

4

Power 990 MW (el.)

South Ukrainian NPP

1

Power 725 MW (el.)

11,9

2

Power 1020 MW (el.)

3

In outage till 11.06.16

Khmelnitsky NPP

1

Power 1010 MW (el.)

12,0

2

Power 1010 MW (el.)

Chornobyl NPP

1

Decommissioning

34,0

2

Decommissioning

3

Decommissioning

 


Outdated Browser
Для комфортної роботи в Мережі потрібен сучасний браузер. Тут можна знайти останні версії.
Outdated Browser
Цей сайт призначений для комп'ютерів, але
ви можете вільно користуватися ним.
67.15%
людей використовує
цей браузер
Google Chrome
Доступно для
  • Windows
  • Mac OS
  • Linux
9.6%
людей використовує
цей браузер
Mozilla Firefox
Доступно для
  • Windows
  • Mac OS
  • Linux
4.5%
людей використовує
цей браузер
Microsoft Edge
Доступно для
  • Windows
  • Mac OS
  • Linux
3.15%
людей використовує
цей браузер
Доступно для
  • Windows
  • Mac OS
  • Linux