There are no violations of NPP safe operation limits and conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal mode.
NPP security divisions and physical protection services are on high alert.
Unit Number | Unit status | On-site radiation level (µR/hour) |
Zaporizhzhya NPP | ||
| In outage till 30. | |
2 | Power 400 MW (el.) | |
3 | Power | |
4 | Power 995 MW (el.) | |
5 | Power | |
6 | Power | |
Rivno NPP | ||
| Power 3 | |
2 | Power 4 | |
3 | Power 980 MW (el.) | |
4 | Power 985 MW (el.) | |
South Ukrainian NPP | ||
| Power 990 MW (el.) | |
2 | Power | |
3 | Power 990 MW (el.) | |
| ||
| In outage till | |
2 | Power | |
Chornobyl NPP | ||
| Decommissioning | |
2 | Decommissioning | |
3 | Decommissioning |
*Since 05.08.20
has being published based on the readings of the nearest detectors of the Automatic Radiation Monitoring
System (ASKRO) instead of the decommissioned system “RADOS”.