08 June, 2018
Published 08 June 2018 07:46
There are no violations of NPP safe operation limits and conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal mode.
NPP security divisions and physical protection services are on high alert.
Unit Number | Unit status | On-site radiation level (µR/hour) |
Zaporizhzhya NPP | ||
1 | Power 920 MW (el.) | |
2 | Power 950 MW (el.) | 11 |
3 | Power 990 MW (el.) | |
4 | In outage till 26.10.18 | |
5 | In outage till 04.08.18 | |
6 | Power 1010 MW (el.) | |
Rivno NPP | ||
1 | Power 415 MW (el.) | |
2 | Power 415 MW (el.) | 10 |
3 | In outage till 04.08.18 | |
4 | Power 990 MW (el.) | |
| ||
1 | Power 985 MW (el.) | |
2 | Power 0 MW (el.) | 12 |
South Ukrainian NPP | ||
1 | Power 995 MW (el.) | |
2 | 11,3 | |
3 | In outage till 19.07.18 | |
Chornobyl NPP | ||
Decommissioning | 34 |