08 July, 2020
Published 08 July 2020 09:28
There are no violations of NPP safe operation limits and
conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal
mode.
NPP security divisions and physical protection services
are on high alert.
Unit Number | Unit status | Аverage dose rate on an industrial site(µSv/h) |
Zaporizhzhya NPP | ||
1 | In reserve until 31.07.2020 | |
2 | Power 665 MW (el.) | |
3 | Power 865 MW (el.) | 0,08 |
4 | In outage till 01.09.2020 | |
5 | In outage till 14.11.2020 | |
6 | Power 970 MW (el.) | |
Rivno NPP | ||
1 | Power 425 MW (el.) | |
2 | Power 405 MW (el.) | 0,10 |
3 | In reserve until 04.08.2020 | |
4 | Power 1000 MW (el.) | |
| ||
1 | Power 820 MW (el.) | |
2 | Power 950 MW (el.) | 0,12 |
South Ukrainian NPP | ||
1 | Power 950 MW (el.) | |
2 | In outage till 31.07.2020 | 0,12 |
3 | Power 600 MW (el.) | |
Chornobyl NPP | ||
Decommissioning | 0,26 |
Performance indicator of NPP Units: