07 June, 2015
Published 07 June 2015 07:39
There are no violations of NPP safe operation limits and conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal mode.
NPP security divisions and physical protection services are on high alert.
Unit Number | Unit status | On-site radiation level (µR/hour) |
Zaporizhzhya NPP | ||
1 | Power 915 MW (el.) | 11,0 |
2 | Power 965 MW (el.) | |
3 | Power 700 MW (el.) | |
4 | In outage till 28.08.15 | |
5 | Power 980 MW (el.) | |
6 | Power 990 MW (el.) | |
Rivno NPP | ||
1 | Power 405 MW (el.) | 10,0 |
2 | Power 400 MW (el.) | |
3 | In outage till 28.07.15 | |
4 | Power 950 MW (el.) | |
South Ukrainian NPP | ||
1 | Power 300 MW (el.) | 12,0 |
2 | In outage till 17.12.15 | |
3 | Power 900 MW (el.) | |
| ||
1 | Power 985 MW (el.) | 12,0 |
2 | Power 945 MW (el.) | |
Chornobyl NPP | ||
1 | Decommissioning | 37,0 |
2 | Decommissioning | |
3 | Decommissioning |