04 June, 2020
Published 04 June 2020 10:44
There are no violations of NPP safe operation limits and
conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal
mode.
NPP security divisions and physical protection services
are on high alert.
Unit Number | Unit status | Аverage dose rate on an industrial site(µSv/h) |
Zaporizhzhya NPP | ||
1 | In reserve until 30.06.2020 | |
2 | Power 1000 MW (el.) | |
3 | Power 995 MW (el.) | 0,11 |
4 | In outage till 01.09.2020 | |
5 | In outage till 14.11.2020 | |
6 | In reserve until 30.06.2020 | |
Rivno NPP | ||
1 | Power 435 MW (el.) | |
2 | Power 420 MW (el.) | 0,10 |
3 | In reserve until 04.08.2020 | |
4 | Power 1005 MW (el.) | |
| ||
1 | Power 870 MW (el.) | |
2 | Power 850 MW (el.) | 0,12 |
South Ukrainian NPP | ||
1 | Power 790 MW (el.) | |
2 | In outage till 31.07.2020 | 0,12 |
3 | Power 600 MW (el.) | |
Chornobyl NPP | ||
Decommissioning |
Performance indicator of NPP Units: