04 December, 2013
Published 04 December 2013 09:01
Unit Number | Unit status | On-site radiation level (µR/hour) |
Zaporizhzhya NPP | ||
1 | Power 1000 MW (el.) | 11,0 |
2 | Power 1000 MW (el.) | |
3 | Power 0 MW (el.) | |
4 | Power 1000 MW (el.) | |
5 | In outage till 15.12.13 | |
6 | Power 1025 MW (el.) | |
Rivno NPP | ||
1 | Power 0 MW (el.) | 9,0 |
2 | Power 420 MW (el.) | |
3 | Power 950 MW (el.) | |
4 | Power 500 MW (el.) | |
South Ukrainian NPP | ||
1 | In outage till 08.12.13, the license validity – 02.12.2023, 275 day of repairs | 11,9 |
2 | Power 1000 MW (el.) | |
3 | Power 1000 MW (el.) | |
| ||
1 | Power 1010 MW (el.) | 12,0 |
2 | Power 1010 MW (el.) | |
Chornobyl NPP | ||
1 | Decommissioning | 36,0 |
2 | Decommissioning | |
3 | Decommissioning |