There are no violations of NPP safe operation limits and conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal mode.
NPP security divisions and physical protection services are on high alert.
Unit Number | Unit status | On-site radiation level (µR/hour) |
Zaporizhzhya NPP | ||
1 | Power 890 MW (el.) | |
2 | Power 930 MW (el.) | 12 |
3 | Power 975 MW (el.) | |
4 | In outage till 26.10.18 | |
5 | In outage till 06.08.18 | |
6 | Power 985 MW (el.) | |
Rivno NPP | ||
1 | Power 410 MW (el.) | |
2 | Power 410 MW (el.) | 10 |
3 | Power 880 MW (el.) | |
4 | In outage till 05.09.18 | |
| ||
1 | Power 990 MW (el.) | |
2 | Power 980 MW (el.) | 12 |
South Ukrainian NPP | ||
1 | In outage till 17.10.18 | |
2 | Power 750 MW (el.) | 12,1 |
3 | Power 950 MW (el.) | |
Chornobyl NPP | ||
Decommissioning | 32 |