03 May, 2017
Published 03 May 2017 06:04
There are no violations of NPP safe operation limits and conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal mode.
NPP security divisions and physical protection services are on high alert.
Unit Number | Unit status | On-site radiation level (µR/hour) |
Zaporizhzhya NPP | ||
1 | Power 820 MW (el.) | 11,0 |
2 | Power 670 MW (el.) | |
3 | In outage till 13.11.17 | |
4 | Power 970 MW (el.) | |
5 | Power 755 MW (el.) | |
6 | Power 1005 MW (el.) | |
Rivno NPP | ||
1 | Power 420 MW (el.) | 9,0 |
2 | In outage till 18.05.17 | |
3 | Power 1000 MW (el.) | |
4 | Power 1005 MW (el.) | |
South Ukrainian NPP | ||
1 | Power 600 MW (el.) | 11,9 |
2 | Power 1015 MW (el.) | |
3 | In outage till 13.07.17 | |
| ||
1 | Power 710 MW (el.) | 12,0 |
2 | Power 1010 MW (el.) | |
Chornobyl NPP | ||
Decommissioning | 35,0 |