02 June, 2015
Published 02 June 2015 06:41
There are no violations of NPP safe operation limits and conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal mode.
NPP security divisions and physical protection services are on high alert.
Unit Number | Unit status | On-site radiation level (µR/hour) |
Zaporizhzhya NPP | ||
1 | Power 935 MW (el.) | 11,0 |
2 | In outage till 06.06.15 | |
3 | In outage till 08.06.15 | |
4 | Power 720 MW (el.) | |
5 | Power 980 MW (el.) | |
6 | Power 985 MW (el.) | |
Rivno NPP | ||
1 | Power 405 MW (el.) | 10,0 |
2 | Power 410 MW (el.) | |
3 | In outage till 28.07.15 | |
4 | Power 965 MW (el.) | |
South Ukrainian NPP | ||
1 | Power 750 MW (el.) | 11,5 |
2 | In outage till 17.12.15 | |
3 | Power 900 MW (el.) | |
| ||
1 | Power 1000 MW (el.) | 12,0 |
2 | Power 935 MW (el.) | |
Chornobyl NPP | ||
1 | Decommissioning | 38,0 |
2 | Decommissioning | |
3 | Decommissioning |