There are no violations of NPP safe operation limits and conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal mode.
NPP security divisions and physical protection services are on high alert.
Unit Number | Unit status | On-site radiation level (µR/hour) |
Zaporizhzhya NPP | ||
1 | Power 920 MW (el.) | |
2 | Power 960 MW (el.) | 11 |
3 | Power 990 MW (el.) | |
4 | In outage till 26.10.18 | |
5 | In outage till 04.08.18 | |
6 | Power 1010 MW (el.) | |
Rivno NPP | ||
1 | Power 400 MW (el.) | |
2 | Power 400 MW (el.) | 10 |
3 | In outage till 04.08.18 | |
4 | Power 985 MW (el.) | |
| ||
1 | Power 1000 MW (el.) | |
2 | Power 990 MW (el.) | 12 |
South Ukrainian NPP | ||
1 | Power 1000 MW (el.) | |
2 | In outage till 08.06.18 | 11,7 |
3 | In outage till 19.07.18 | |
Chornobyl NPP | ||
Decommissioning |