01 August,2020
Published 04 August 2020 13:26
There are no violations of NPP safe operation limits and
conditions.
Radioactive situation meets established norms.
Systems of NPP physical protection work in normal
mode.
NPP security divisions and physical protection services
are on high alert.
Unit Number | Unit status | Аverage dose rate on an industrial site(µSv/h) |
Zaporizhzhya NPP | ||
1 | In reserve until 07.08.2020 | |
2 | Power 670 MW (el.) | |
3 | Power 980 MW (el.) | 0,08 |
4 | In outage till 01.09.2020 | |
5 | In outage till 14.11.2020 | |
6 | Power 980 MW (el.) | |
Rivno NPP | ||
1 | Power 435 MW (el.) | |
2 | Power 410 MW (el.) | 0,09 |
3 | In reserve until 04.08.2020 | |
4 | Power 990 MW (el.) | |
| ||
1 | Power 1005 MW (el.) | |
2 | Power 910 MW (el.) | 0,12 |
South Ukrainian NPP | ||
1 | Power 805 MW (el.) | |
2 | Power 750 MW (el.) | 0,118 |
3 | In outage till 03.08.2020 | |
Chornobyl NPP | ||
Decommissioning | 0,35 |
Performance indicator of NPP Units: